Planning, Design and System Requirements


    The BUOU-AS team held a meeting with the project manager and adviser. We requested the system requirements. We divided the workflow per module.

    
    Meeting with the whole web dev team. Project manager Adrian Bonaobra introduced the PHP framework we are gonna use for the development.

    Online meet for project assignment and discussion of the requested system requirements. Our team was assigned to develop the Online Admission System for Bicol University-Open University

    We drafted the sample UI for the system. I was tasked to accomplish the sample database and its table relationships.

    Another online meet for final project requirements and setting of timeframe for designated days to complete the modules and the documentation. Started studying about Laravel framework, Github and its commands.
 
    Started creating repositories and learning about pull requests, commits and branches. Initialized working with remote repositories in my local machine and cloning them as local copies of the repository.                   